So, my life for the next five weeks ->
Technical
June 18 - 22
- Define screens to complete for conference - CHRIS
- Finalize application name & reserve domain name - CHRIS, CURT, JIM
- Begin import process documentation - CURT, KEN, CHRIS
June 25 - 29
- Setup development server - DB & Web. Link <name>.dev.xcalibur.com - CHRIS
- Finalize requirements for screens that will be developed for conference - CHRIS, CURT
- Finalize import requirements - CURT, KEN, CHRIS
- Finalize other "non-essential for July" requirements, including use cases - CHRIS
July 2 - 6
- Build out of screens continues - CURT
- DB ERD continues - CURT
July 9 - 13
- Finalize screen buildout - CURT
- Setup staging server - DB & Web. Open port through firewall & link <name>.stag.xcalibur.com <tentative> - CHRIS
July 16 - 20
- Choose external hosting company - JIM, CHRIS
- Penultimate final DB ERD & Data dictionary - CURT
July 22 - 27
- CONFERENCE!
Conference
June 18 - 22
- Presentation - define list of APR challenges - CHRIS
- Booth - practice setup of booth - CHRIS, JIM
- Booth - develop draft design - CHRIS, JIM
- Swag - order shirts - JIM
- Swag - choose other give aways - CHRIS, JIM, CURT
June 25 - 29
- Presentation - draft due - CHRIS
- Presentation - reserve 2nd projector - JIM
- Booth - begin draft content for booth - CHRIS, JIM
- Booth - Draft brochure content - CHRIS, JIM
July 2 - 6
- Presentation - begin penultimate final - CHRIS
- Booth - continue draft content - CHRIS
- Booth - order give aways - CHRIS, JIM
July 9 - 13
- Presentation - finalize penultimate final - CHRIS
- Booth - finalize content for booth - CHRIS
- Booth - receive swag give aways
July 16 - 20
- Presentation - Final & practice presentation w/ AED - CHRIS / ALL
- Booth - final design printed - JIM, CHRIS
July 22 - 27
- CONFERENCE!