5 week plan - through July 22nd conference

So, my life for the next five weeks ->
 
Technical
June 18 - 22
  •  Define screens to complete for conference - CHRIS
  •  Finalize application name & reserve domain name - CHRIS, CURT, JIM
  •  Begin import process documentation - CURT, KEN, CHRIS
June 25 - 29
  • Setup development server - DB & Web.  Link <name>.dev.xcalibur.com - CHRIS
  • Finalize requirements for screens that will be developed for conference - CHRIS, CURT
  • Finalize import requirements - CURT, KEN, CHRIS
  • Finalize other "non-essential for July" requirements, including use cases - CHRIS
July 2 - 6
  • Build out of screens continues - CURT
  • DB ERD continues - CURT
July 9 - 13
  • Finalize screen buildout - CURT
  • Setup staging server - DB & Web.  Open port through firewall & link <name>.stag.xcalibur.com <tentative> - CHRIS
July 16 - 20
  • Choose external hosting company - JIM, CHRIS
  • Penultimate final DB ERD & Data dictionary - CURT
July 22 - 27
  • CONFERENCE!
 
Conference
 
June 18 - 22
  • Presentation - define list of APR challenges - CHRIS
  • Booth - practice setup of booth - CHRIS, JIM
  • Booth - develop draft design - CHRIS, JIM
  • Swag - order shirts - JIM
  • Swag - choose other give aways - CHRIS, JIM, CURT
June 25 - 29
  • Presentation - draft due - CHRIS
  • Presentation - reserve 2nd projector - JIM
  • Booth - begin draft content for booth - CHRIS, JIM
  • Booth - Draft brochure content - CHRIS, JIM
July 2 - 6
  • Presentation - begin penultimate final - CHRIS
  • Booth - continue draft content - CHRIS
  • Booth - order give aways - CHRIS, JIM
July 9 - 13
  • Presentation - finalize penultimate final - CHRIS
  • Booth - finalize content for booth - CHRIS
  • Booth - receive swag give aways
July 16 - 20
  • Presentation - Final & practice presentation w/ AED - CHRIS / ALL
  • Booth - final design printed - JIM, CHRIS
July 22 - 27
  • CONFERENCE!